Campinas - SP

alt

 

Investments for the 2014 World Cup

Foreseen Actions:
- Construction of the New Passengers Terminal and Ground Area (1st Phase)
Completion: July 2012
Status: Projects under bidding process


- Implementation of the Operational Module
Completion: August 2011
Status: Completed

 

Total investment: R$ 873.05 million

 

Actions planned:

- Construction of New Passenger Terminal and Aircraft Patio

- Adequacy of Existing Passenger Terminal

- Renovation and Expansion of Systems tracks and Patios


 

Operational Data

2010

2014

Passengers terminal (m2)

25.215

103,982

Capacity of terminal (year)

9,3 million

23.8 million

Demand Passengers/year

7.5 million

9,5 million

Airplanes Ground Area (m2)

190,051

568,596

 


See more